Posted on: May 3, 2021

[ARCHIVED] Council considering water & sewer rate increases

GW Plant

CLARKSVILLE, Tenn. –  City Council members are considering water and sewer treatment rate increases proposed by Clarksville Gas & Water designed to cover the costs of building a new water treatment plant and making other necessary improvements to the water and sewer systems.

Gas & Water General Manager Mark Riggins told the City Council on Thursday that Clarksville must spend $177.5 million over the next several years to expand and improve the water system. Another $70 million is needed to upgrade the sewer treatment system, including some $14.5 million to add a sophisticated sludge-drying system at the wastewater treatment plant. The drying equipment will decrease Gas & Water’s output of sludge, alleviating volume and odor issues at Bi-County Landfill.

The big ticket item on the project list is $138 million to build a long-planned second water treatment plant. And some of the work to the sewer system is overflow mitigation projects, which are needed to comply with state consent orders. 

“State regulations require that we add a new water treatment plant when our current plant reaches 80 percent capacity, and because of our growth and success as a community, we’re very close to that point,” Riggins said.

The City has purchased a site for a new North Clarksville water plant on the Cumberland River off of Barge Point Road. Some $6.8 million has already been spent for the land and to begin engineering and design of the new water treatment plant. The City’s sole water treatment plant, off Ashland City Road/US 41A Bypass, will be expanded one last time, but then it will have reached its physical capacity.

“We have a tremendous amount of work scheduled to keep our water and sewer systems performing at the necessary levels, and these rates are designed to generate sufficient revenue to cover our future costs,” Riggins said.

The rate study was conducted by Raftelis Financial Consultants Inc., a leading utility management consulting firm. Rates were analyzed on whether a customer is inside or outside the City and based on three classifications -- residential, commercial and industrial. 

The rate increases would be phased in over the next four years, with the first jump occurring July 1, 2021. Under the proposal outlined by Riggins, the average in-city residential water and sewer bill would increase $3.14 per month in the first year, and then increase each July 1 in smaller increments through 2024.

The average in-city residential customer has a ¾-inch water meter and uses 4,000 gallons of water per month. That customer currently pays a monthly bill of $54.44. That would rise to $57.58 per month in July 2021 and top out at $64.37 per month after July 2024.

The average outside-the-city residential customer, with a ¾-inch water meter and 4,000 gallons of water usage per month, currently pays a monthly bill of $ $93.22. That would rise by $1.93 per month to $95.15  in July 2021 and top out at $102.15 per month after July 2024.

Similar percentage increases would occur to commercial and industrial rates. Proposed meter charges and rate tables for all classifications, plus a list of planned water and sewer projects,  are available for review here.

Overall, Riggins said the rate study had several broad goals:

  • Generate sufficient revenues to cover system costs.
  • Adjust base water meter charges to recover customer service and meter-reading costs.
  • Develop in-city and outside-the-city rates applicable to all customer classes.
  • Gradually close the gap between in-city and outside-the-city rates. Under this proposal, outside-city rates, which had been double the in-city rates, would be 75 percent higher than in-city rates.
  • Eliminate a tiered system that had existed for wastewater rates.

“Our goal over time is to continue to align in-city and outside-city rates,” Riggins said. “But, because of how our rates have historically been structured, we can’t do that all at once.”


Facebook Twitter Email

Other News in All News

O11

Clarksville elected officials sworn in

Posted on: January 5, 2023
20220420-Parking-Meters-8023

Free parking downtown until May 2

Posted on: April 22, 2022
Weather Report Jan. 6

City offices working remotely

Posted on: January 6, 2022
City Mayor Joe Pitts

Mayor’s 2021 Thanksgiving Message

Posted on: November 23, 2021
Clarksville Thanksgiving JPG

City offices to close for Thanksgiving

Posted on: November 22, 2021
Mayor Pro Tem Smith

Frosty Morn Community Meeting Success!

Posted on: November 19, 2021
GFOA Certificate 2021

City earns 3 top financial recognitions

Posted on: October 18, 2021